Lake Rotorua PC10 Catchment Modelling
The three pilot sub-catchments (Puarenga, Hamurana, Waingaehe) within the wider Lake Rotorua catchment, showing the mismatch between BOPRC’s surface-water catchment delineation and GNS’s groundwater sub-catchment delineation.
Client: Bay of Plenty Regional Council
Phase 1 of the Lake Rotorua integrated catchment modelling programme was a scoping study to identify a catchment modelling framework capable of providing scenario-ready lake model inputs under Plan Change 10 (PC10), which sets a Trophic Level Index target for Lake Rotorua requiring a sustainable nitrogen load of ~435 tN/yr.
Lake Rotorua’s water quality is governed by slow-moving groundwater with transit times of decades to over a century, and roughly 45–60 km² of groundwater catchment extends beyond the surface-water topographic boundary. We reviewed candidate modelling platforms against five criteria — incongruous groundwater/surface-water boundaries, multi-decade concentration lags, surface water-groundwater interaction, chemistry at the lake edge, and response to changing land use and climate — and built minimal-complexity pilot models of three sub-catchments (Puarenga, Hamurana and Waingaehe) using the two most promising frameworks, SWAT+gwflow and the legacy SWAT2012-MODFLOW-RT3D coupling.
Both frameworks ran stably over a 44-year simulation period, but neither could fully meet the project’s requirements: SWAT+gwflow’s single unconfined groundwater layer cannot extend beyond the surface-water catchment or resolve multi-decade lags, while SWAT-MODFLOW-RT3D can represent a larger groundwater domain and multi-layer flow but lacks a working dynamic land-use workflow and was found to have reactive-transport bugs affecting nitrate and phosphorus output. Based on these findings, Phase 2 is redirected toward a bespoke, semi-distributed catchment model in the lineage of NIWA’s ROTAN, built on groundwater catchments with tritium-calibrated transit-time distributions and time-varying land use.